Work involves the activities as shown in the table. Completion of activities C and E is deliverable.A 5 day, 40 hour week, is to be worked. The project started on Monday 2nd August 2020.

Activity

Predecessors

Duration

(Days)

Workers needed

($50/Hour)

Machines needed

($100/Hour)

Percent completed

after 8 working days

A

10

4

2

77

B

2

15

5

100

C

A

1

10

4

0

D

8

4

0

82

E

A

4

8

2

0

F

A, D

12

8

2

0

G

D

5

7

1

0

H

C, E

10

10

3

0

I

F, G

3

4

0

0

Use MS Project to analyse the project.

a) What is the estimated completion date for the project?

b) What is the estimated date to achieve the deliverable?

c) What is the total estimated cost of workers and machines for the project?

d) What is the estimated cost of workers and machines for the work completed after 8

working days?

e) After smoothing the project within the available slack, what is the minimum number

of workers required to complete the project by the same date?

Solution:

15% off for this assignment.

Our Prices Start at $11.99. As Our First Client, Use Coupon Code GET15 to claim 15% Discount This Month!!

Why US?

100% Confidentiality

Information about customers is confidential and never disclosed to third parties.

Timely Delivery

No missed deadlines – 97% of assignments are completed in time.

Original Writing

We complete all papers from scratch. You can get a plagiarism report.

Money Back

If you are convinced that our writer has not followed your requirements, feel free to ask for a refund.