Open with ZIP Extractor Micheal heads a team of engmeers in a project to improve and increase the functionality of a microwave product. It is targeted that the improved microwave can overtake the sales of pressure cookers. In order to successfully execute the project ten activities need to be completed according to the conditions in Table 1. [Micheal mengetuai sepasukan jurutera dalam satu projek untuk menambahbaik dan meningkatkan fungsi produk ketuhar gelombang mikro. Adalah disasarkan jualan ketuhar gelombang mikro yang telah ditambahbaik akan dapat mengatasi jualan periuk tekanan. Untuk memastikan kejayaan projek ini, sepuluh aktiviti perlu dilengkapkan dengan syarat-syarat seperti di dalam Jadual 1.] Table 1 (Jadual 1] Predecessor [Pendahulu) Activity [Aktiviti] P Q R S T U V W X Y P P P Q&R S S&T U V & W Duration (days) (Tempoh] 5 4 3 4 6 4 5 6 6 4 a. With the aid of a network diagram, determine the minimum time to complete the project. [Dengan bantuan gambar rajah rangkaian, tentukan masa yang minimum untuk menyiapkan projek itu.] (12 Marks / Markah) b. Which activity can withstand the most delay without affecting the project duration? Justify your answer with appropriate calculations. [Tentukan aktiviti Pagerup3 va Ien12 gung kelewatert + tanpa menjejaskan tempoh projek? Berikan kewajaran jawapan anda dengan pengiraan yang sesuai.)